x

ODC Horotiu

This two stage contract to a green fields site just north of Hamilton, once again called on Fire Solutions expertise to design, supply and install, and commission the fire systems to the new drier building together with interfacing directly with the client to provide a certifiable fire water supply, consisting of fire pumps and tanks.

Spread over a very demand construction period of only 8 months Fire Solutions meet all of the project demands.

The systems included Fire Sprinkler, Tail End Pre Action Dry Pipe Systems, Automatic and Manual Fire Alarms, Fire Hydrant Systems, Early Waring Smoke Detection, Fire Pumps, Fire Alarms to intrinsically safe areas, and interfaces to the buildings drier deluge

All of the above being carried out by our in-house design, project management, construction/installation and commissioning teams.

Contract Value $ 750,000                              Completion Oct 2018